Haskovo, Bulgaria: Haskovo Municipality has recently informed all the residents and guests through its social media account that a temporary movement organization is being introduced to implement the project “Repair of the flooring on Blvd. “G. With. Rakovski”.
The Repair of the Blvd. Rakovski will be performed in 5 stages. The repair activities will begin with implementing the first stage on Monday, August 14, 2023. , from 7.30 pm in the eastern sage of the Boulevard, in the section between the Blvd. “Junction” and St “The Danube”.
Movement in the site will be complex; the work will sometimes cover both lanes of the canvas. The activities will continue until 4:30 pm every day, including Saturday. After this hour, the movement on the canvas will be restored. A signalling will be placed, patrolled and assist by KORZ sector teams and Road Police officers.
The created temporary organization on the site also provides changes in the movement of urban transport. Trolleybuses No. 108 and No. 308 will be replaced by buses. During the repair time, from 7.30 to 4.30 pm, the route is ZMM – Bus Station – Street “Bulair” – st. Danube – Blvd.
“Rakovski”. The bus on route 104 changes from the First Polyclinic / DCC 1/ – Blvd. “Bulgaria” – Blvd. “In. Levski” – street Danube – Boulevard “Rakovski”.
After 16.30 hours, when the repair works are over, the traffic of both cars and urban transport is restored through the site under repair throughout the entire period of restoration of the flooring on Blvd. Rakovski cars of the Fire Service, Emergency Aid and the Ministry of Interior authorities will be skipped.
The following stages of the renovation of the Boulevard will be performed as follows: eastern canvas of Blvd. Rakovski at the stretch of the street. Danube to the street “Com”, western canvas on Blvd. Rakovski from the street Com to the Danube, western canvas from the street. Danube to the Blvd. “Union”, repair of the flooring at the roundabout of Blvd—Rakovski with street Kom to the end of the Boulevard, gas station OMV.
The Municipality of Haskovo apologized to all residents and guests of Haskovo for the temporary inconvenience created due to the repair of the Blvd. flooring “G. With. Rakovski”. The main activities will be carried out in phases and completed within one month.