Chepelare, Bulgaria: The Municipality of Chepelare informed through their official Facebook account that 11 projects with building permits have been prepared and agreed upon, covering the infrastructure of all settlements in the municipality of Chepelare. Another 5 infrastructure sites are being prepared for issuing a construction permit in the town. Chepelar, s. The conifer, s. View and s. Zornitsa.
Before the final repair works on the street “9th September” in the village Juniper 291 m long, curbs and sidewalks have been replaced, finishing tomorrow and on Friday, weather appropriate; the second layer of asphalt flooring is to be installed to complete the site and the street network in the village of 1000 sq.m. is currently getting fixed.
The dredging of street networks in Pavelsko, Malevo and Orehovo villages will continue. The town of Chepelare is actively working in the interblock space in the Skior blocks 3, 4 and 5. The aim is to replace depreciated sidewalks, curbs, interblock asphalt roads and surface water drainage.
The seats in the stands at the mini-football field at Vasil Dechev Primary School in Chepelare have been set, and the adjacent sidewalk and railing are currently being restored. Work will begin next week on the implementation of the large-scale renovation project of the sports court at the tennis courts.
Bogutevo is about to complete the plumbing network in the village, which started last year – branches 1 and 3 and 2 and 4 are completed. In the towns of Lilekovo and Ostrica, the phased replacement of the water network is expected, as well as the street network’s patching from the beginning of the village Bogutevo.
Pamporovo is due to the completion of a street at Sokol Hotel and Arfa Hotel in a section of about 200 meters with the replacement of asphalt flooring.
The Municipality mentioned that they will inform the residents about the progress of infrastructure activities on the official Internet and Facebook pages of Chepelare.